JOULE ENERJİ A.Ş. (December 2013 – April 2016 ) :

  • Libya Awbari 640 MW SCPP (Piping & Aux. Equipments) (Dec. 2013-Jul. 2014)
  • IGSAŞ Heat Exchanger Maintenance (Site Manager) (Jul. 2014 – Sept. 2014)
  • Georgia Gardabani 240 MW CCPP (Cooling Tower, ST Piping, Commissioning) (Sept. 2014 – Jul. 2015)
  • Ambarlı CCPP Maintenance (Site Manager) (Jul. 2015 – Jul. 2015)
  • Centeral Office Technique Department (Quotations and Techincal R&D) (Jul. 2015 – Feb. 2016)
  • Libya Al-Khums 550 MW SCPP (GE Piping) (Feb. 2016 – April 2016)

 

Libya Awbari 640 MW SCPP:
Awbari 640 MWAwbari 640 MWAwbari - with Guenter (siemens piping sv)Awbari Quality CheckAwbari Siemens Combustion Chamber

 

İGSAŞ:
Damaged Heat Exc.İgsaş
İgsaş wide

 

Georgia Gardabani 230 MW CCPP:

Georgia Cooling Tower ProjectGeorgia 230 MW Piping

cooling towerGardabani Cooling Tower  Georgia Gardabani 230 MW CCPPGardabani BOP Systems        ST Commissioning  Commissioning

Libya Al-Khums 550 MW SCPP:

9432f9ea61706b3e61c19339e6197e67568